|
|
MINIHYDRO POWER PROJECT |
Mini
Hydro power project, Polis is the major and tremendous
achievements of IRDWSI, during the year 19990-2000. according to
the power demand analysis to Putsil villagers, the proposed mini
hydro power project is now in action. it is therefore reasonable
to expect a high surface run off during the rainy season resulting
in they still load in stream water.
The project successfully completed because of the people's
contribution and dedication of their work with a strong commitment
unity among them. From the beginning of the progarmme the whole
village people. around 200, including women and children worked
hard till the completion of the project.
To meet the financial barrier of the maintenance of the project.
Villagers arranged a fund by collecting a minimum of Rs.20/- from
each house per month. |
Mini Hydro Power Project - Follow Up |
The
follow up activities of the Mini Hydro Power Project of Putsil village is a regular
programme. At the initial phase the
Hydro project functioned smoothly without any defects. Problems
cropped up only after one year. Gradually, from then onwards
various kinds of minor problems followed one after the other. The main problems were
a) Cable Problem
The
1300 metres aluminium armour cable used as transmission line from the power house to the village often get short circuited during
rainy days due to faulty displacement at the time of laying the cable
underground. As the cable was under the earth ft was very difficult to locate the
exact spot as the team lack the regulatory mechanisms needed to evaluate such event. At present, it is administered by cutting the cable wire at four different locations and ensure
regular continuity test. Under such circumstances, once the short circuited sites were identified the two ends of the cable
were easily attached by using M-seal cable joint . As a result of the above loopholes, current transmission
was interrupted in the entire area consecutively for a week. A decentralized
policy was adopted
for maintenance and operational work. Often technicians from
outside were hired to repair the damages. Technical
assistance has been provided by the core staff. They
constituted a village level committee members to foresee smooth
functioning of the project and to tackle any matter arising out of
it.
|
|
|
(b) Voltage Drops After Lighting Load
In
the evening when there was heavy load of current, the voltage tend
to drop drastically from 415v to 340v. After an enquiry it
came to light that the sudden fall of power was attributed to the
use of excessive fluorescent lamp. In order to bridge this
lacuna decision was made to affix additional power with a capacity
of 10 KVAR at the distributing end to check the voltage stumble.
A 10 KVAR capacity of L&T has been purchased for this purpose.
|
|
|
(c) Low Turbine Speed
The
peltron turbine consisted of two nozzles. When the two
nozzles were in operation the speed of the turbine tends to slow
down. At normal speed, when one nozzle was operated, the
speed of the turbine is 980 RPM. But when both the nozzles
were operated at the same time the recorded speed was 720 - 750
RPM. But it was supposed to maintain the same RPM. In
order to match the discrepancy, a study was conducted on the flow
of water in the pen stock with the help of an expertise Mr. Sunith.
After completing the study it was decided along with the
consultant of the project M/s Aroville Energy Products, to minimize
the size of one of the nozzle. The top nozzle (N2)
size was reduced to Y2 of that of the lower nozzle. Finally,
after repairing and induction of smaller size nozzle, the problem
was solved and power restored.
|
(d) Defective Electronics Load Controller
The
generator is connected with 3 Electronics Load Controller in three
phases which controls automatically the frequency of the generator
out put. It also indicates whether the turbine is low, high
or normal. Due to lightning hit 2 of the 3 ELC were not
functioning. Therefore, the load of the generator needs to
be cautiously maintained by the responsible technicians. At
present adjustment was made. The project is not in
possession of the spare parts required. Spare parts have
been already requested and notified to the supplier of ELC, who in
turn, have to import the spares. Rectification work will be
immediately set out once the goods are delivered. Apart from
this, maintenance work on other parts were carried out. The
technicians clean the generator carbon brush & slip ring,
removal of silt deposits in the check dam and ensure steady water
flow inside the channel. Electricity consumer fund was
initiated in the village. So far, the total amount of funds
collected under the consumer funds is Rs. 21,000. Recently,
an extra shaft was purchased from the market to replace the
existing one, as it was bent and corroded the same was replaced.
|
Mill House - Putsil |
With
the access of electric power, a mill house was set up to cater to
the needs of the people. The aims was to cater to its
neighbouring villages. Machines for grinding, rice
hulling, flour mill and oil extraction were housed at the Mill House. Construction
of the mill house was completed in the
month of May. But due to lack of trained personnel among the
villagers the machines could not be operated. Besides the additional revenue accumulated
from servicing the mill, the work load of women are on the
decrease, as traditionally, in a Adivasi society daily chores like
pounding-of rice and pulses are considered to be the manual
responsibilities of the women.
Computer
accounting format was developed to maintain accounts.
Village committee was set up to manage the mill. They
selected 3 landless persons ( 2 male & I female women) to run
the mill. Certain amount was fixed for every grain processed
in the mill. The amount collected as revenue from the
services of the mill, 50% of the total amount will be paid to
those in charge of the mill. Another 25% will be deposited
to the electricity consumer fund and the remaining balance (25%)
will be earmarked for mill house maintenance. At present,
rice huller operates efficiently . For flour mill & oil
explorer, one trainer is yet to be recruited for a month to train
the village personnel who are in charge of the whole operations.
|
Solar Home System - Panasput |
The
core team follow-up the solar home system which was given to the
villagers as an experiment to study the feasibility of its long
term loan basis. Out of the 1 0 solar lanterns 6 of them
were not functioning. However, the disorder was due to
faulty handling of the equipment by the person-in-charge rather
than other defects of the technology. As a consequence, the
repayment of loan could not be recuperated as envisaged upon.
After
a meeting with the village community it was decided that the
equipment will be handed over to some other person who is
competent enough to take care. The aim of the experiment is
to develop the renewable energy option, and if successful,
integrate into income generation programmes as part of it.
Besides
this follow up programme, core staff attended meetings on health,
water and sanitation conducted by DST, New Delhi. A project
proposal on sanitation & safe drinking water facilities for
Barakotni village was prepared and submitted to the Government.
TOP
|
|
|
|